Bulgarian Energy Minister: On October 1, Gas will flow through the Interconnector from Greece

Energy | August 12, 2022, Friday // 16:26|  views

ICGB interconnector

Gas will flow through the interconnector from Greece on October 1”. This was stated by Energy Minister Rosen Hristov after the meeting of President Rumen Radev with the owner and management of the construction company building the intersystem gas connection with Greece - "Avax" and the contractor - ICGB.

There is some confidence that the project will be completed and commissioned on time. The builder has made all the commitments that the commissioning will be on time - commercial quantities of gas should flow through the pipe on October 1", emphasized the Minister of Energy.

According to him, what worries him is that the builder could not provide a schedule for the implementation of absolutely all activities. "We agreed that on Wednesday we will have a meeting at the site and there they will provide me with the schedule I require – agreed with the builder, subcontractors if there are any for the specified activities and the contractor - in the case of ICGB, which schedule will be checked by the Ministry of Energy and Ministry of Regional Development and Public Works. We will then operationally monitor each activity according to this schedule”.

"If the builder really works at an intensive pace - this deadline - until the beginning of September - to complete the construction activities, as the company ‘Avax’ claims, most likely this deadline can be normal", the Minister of Regional Development and Public Works Ivan Shishkov.

"At the moment, intensive work is being done between the National Building Control Directorate and the supervisor and the documentation has been completed to clear the issue with the stages so that we can put it into operation," he added. "To date, some of the problem points have started to clear up".

The builder of the gas connection with Greece to Radev: Within August we will fulfill everything from our side

President Rumen Radev met with the owner and management of the construction company building the intersystem gas connection with Greece and the management of the project company that commissioned the construction. Clarifying the real situation and the necessary actions for the fastest and most efficient completion of the project will be the focus of the conversation.

Acting Prime Minister Galab Donev, Acting Minister of Energy Rosen Hristov and Acting Minister of Regional Development and Public Works Ivan Shishkov took part in the meeting.

"The Intersystem Gas Connection is not just an infrastructure project, it is an object with a strong regional and geopolitical dimension. This project is essential not only for deepening the strategic partnership between our two countries but also has its great significance for achieving real diversification in gas supplies to Bulgaria and the countries of Central and Eastern Europe. Also to guarantee stable economic development in our region and to implement the European policy to guarantee independence and security of supplies of energy carriers," said Radev.

живо среща газовата връзка гърция президента

The completion of this infrastructural and geopolitical project in the conditions of a severe global energy crisis, of limited supplies, rising prices, is of particular importance for our country”, emphasized the president.

He assured that the Bulgarian side is ready for full assistance to put the project into operation as quickly as possible. He stated that he hoped that the remaining finishing works and construction and installation works related to fire safety and activities related to the safe operation of the project would be completed with full mobilization, both of the builders, the contracting authority, and with the support of the Bulgarian state, in the person of the Bulgarian government.

On behalf of the “Avax” construction company, they assured that from the very beginning they were aware of how important the project was and were trying to do their best to complete it successfully. They informed that at the end of 2020, at the height of the coronavirus epidemic, 35 highly qualified specialists fell ill and they did not know where people should stay in quarantine - in Bulgaria or in Greece.

"In such difficult conditions, we realized how important this project is for Bulgaria and we will do everything possible to make Greece proud of its implementation. We will do everything in our power so that the site can be completed and successfully put into operation," the company said.

It became clear that the builder has made a time estimate on how to make the completion happen in the most expeditious way and within August they will try to have everything done on their side. They assured that there is a 2 year warranty support period.

The project is on the final stage, said Teodora Georgieva - executive director of the contracting authority ICGB.

"We expect the site to be handed over to us by the builder, ready for operation, in accordance with all the requirements of the Bulgarian legislation. The main activities have been completed, but there are accompanying activities that are mandatory in order to legalize the project," she said.

Georgieva specified that they are currently in discussion with "Bulgargaz" when exactly to activate the Komotini point for gas extraction of Azeri gas.

Follow Novinite.com on Twitter and Facebook

Write to us at editors@novinite.com

Информирайте се на Български - Novinite.bg

/Nova, BNT

We need your support so Novinite.com can keep delivering news and information about Bulgaria! Thank you!


Tags: interconnector, gas, greece, Bulgaria

Back  

» Related Articles:

Search

Search