Lot 2 of Bulgaria’s Struma Motorway To Be Completed in Autumn of 2015

Business | September 30, 2014, Tuesday // 15:57|  views

Ekaterina Zaharieva, caretaker Deputy Prime Minister and Regional Development minister, photo by BGNES

Lot 2 of the Struma motorway will most probably be completed by the autumn of 2015, according to Bulgaria’s caretaker Regional Development Minister Ekaterina Zaharieva.

Zaharieva inspected Tuesday the 37.5km motorway section from Dupnitsa to Blagoevgrad.

Zaharieva, caretaker Transport Minister Nikolina Angelkova, and Lazar Lazarov, Chair of the Managing Board of the Road Infrastructure Agency, visited the Dupnitsa–South road junction, the archaeological excavations near the western village of Mursalevo and the tunnel at Kocherinovo, according to reports of dnevnik.bg.

After the inspection, Zaharieva declared that it was one of the best examples of organization of the construction of a motorway, adding that everything proceeded on schedule.

Lot 2 of the Struma motorway is being built by a consortium of Italian Impesa and Bulgarian GBS-Infrastructure Construction and Patstroi 92. The value of the contract is BGN 358.7 M.

Later on Tuesday, the ministers will check the progress of construction works at the problematic Lot 4 between Sandanski and Kulata, which is being built by Greece’s Aktor under a contract worth BGN 67.2 M.

Several inspections revealed that no construction works were underway at the site and the contractor was warned that the agreement would be cancelled if the delays persisted. The 16km motorway section was to be launched by October 15.

 

We need your support so Novinite.com can keep delivering news and information about Bulgaria! Thank you!


Tags: Ekaterina Zaharieva, caretaker government, Struma motorway, Road Infrastructure Agency, Lazar Lazarov, Nikolina Angelkova

Back  

» Related Articles:

Search

Search