Bulgaria's Nuclear Plant Back in Business by November 6

Energy | October 23, 2010, Saturday // 13:31|  views

Bulgaria's Economy and Energy Minister, Traicho Traikov, announced Unit 6 of the Kozloduy Nuclear Plant would be re-launched on November 6 thanks to a fast delivery of spare parts from Russia. Photo by BGNES

The spare parts needed by Bulgaria's Nuclear Power Plant (NPP) Kozloduy arrived in Bulgaria overnight with an IL-16 aircraft of the "Volga-Dnepr" airline, the Bulgarian National Radio, BNR, reports Saturday.

Minutes after the plane's landing, at 2 am local time at the Sofia airport, the pipes have been loaded on trucks, which left for the Danube town of Kozloduy. Their installation is to last about one week, experts say.

On October 19, Economy and Energy Minister, Traicho Traikov, announced that a problem with one of the two functioning reactors of Bulgaria's Kozloduy Nuclear Power Plant (NPP) - Unit 6, can trigger serious delays in its switching back to the country's electric network.

A check of the system managing the reactor's safety protection located damage in the equipment's cap and the need of replace 31 out of 61 pipes total.

The new parts were shipped by the manufacturer – the Russian "Hydropress" owned by Rosatom.

Traikov said at the time that each day of the delay would amount to BGN 1.5 M in losses.

Initially, the Russian company replied they would need about 7 to 8 months to make and deliver the parts, however, after not only the Minister's interference, but also the personal one of Prime Minister, Boyko Borisov, who spoke on the phone with his Russian counterpart, Vladimir Putin, the fast delivery was given a green light.

In an interview for Darik radio Saturday, Traikov said Unit 6 would be back in business by November 6.

Unit 6 was turned off for its scheduled annual repairs and refueling on September 18 and was expected to begin functioning again at the end of October.

We need your support so Novinite.com can keep delivering news and information about Bulgaria! Thank you!


Tags: NPP, Kozloduy, Boyko Borisov, Vladimir Putin, damage, NPP, NPP Kozloduy, Traicho Traikov, Economy and Energy Minister, repairs, delay, Unit 6, Unit 6

Back  

» Related Articles:

Search

Search